European Customer Witnesses FAT at Shenyang Taige Oil Equipment

Shenyang Taige Oil Equipment Co., Ltd. (Taige) recently hosted a delegation of European engineers and quality assurance specialists at its manufacturing facility in Shenyang, Liaoning Province. The purpose of the visit was to conduct a comprehensive Factory Acceptance Test (FAT) on a customized cementing test equipment unit, rigorously verifying its compliance with the specifications outlined in the purchase order. This visit marks a significant milestone in Taige’s international business operations, underscoring the company’s commitment to quality assurance and customer satisfaction on a global scale.

Purpose of the Factory Acceptance Test (FAT)

The Factory Acceptance Test serves as a critical quality gate in the procurement of industrial equipment. For the visiting European client, the FAT is the final, verifiable step before the equipment is disassembled, packaged, and shipped. The primary objective of this inspection was to provide tangible evidence that the fabricated cementing test equipment meets all agreed-upon technical, operational, and safety standards. The delegation’s mandate was clear: confirm the equipment’s conformity against the purchase order specifications and witness the operational integrity of the system under simulated working conditions.

cementing test equipment

Detailed Inspection Process and Documentation Review

The engagement began with a structured documentation review, a cornerstone of any rigorous FAT. The Taige project management team presented a complete data book, including material test certificates (Mill Sheets), pressure test charts, welding procedure specifications (WPS), and the qualifications of welding operators (WPQ). The European auditors meticulously cross-referenced these documents against the requisition numbers and drawing revisions specified in the purchase order. This step was followed by a physical inspection of the equipment, where the team verified the correctness of the mechanical assembly, the integrity of hydraulic and pneumatic connections, and the conformity of the instrumentation.

SGSA, MSGSA, UCA

Functional and Operational Testing Phase

Following the static checks, the focus shifted to functional testing. The cementing test equipment was powered up, and the delegation witnessed a series of operational protocols. This included the calibration of pressure transducers and flow meters, which were benchmarked against certified master gauges. The test team simulated the cementing operation under varying pressure and temperature regimes to ensure the equipment’s control logic, safety interlocks, and emergency shutdown systems responded precisely as designed. The equipment successfully completed the full battery of tests, with performance data logging confirming the unit operates within the tight tolerances stipulated in the technical proposal.

stirred fluid loss 微信图片_20260908080401_25_2